v1
latestOpenAPI 3.0.12026-07-24241275527.9 KBDependencies
Modify Dependency
Change relationType of task dependency.
<b>Scopes:</b> Default, wsReadWrite
put/dependencies/{dependencyId}
Path parameters
dependencyIdstring required
Query parameters
relationType'FinishToFinish' | 'StartToStart' | 'StartToFinish' | 'FinishToStart' required
- FinishToFinish - Finish to finish. Allowed only when predecessor and successor are Planned or Milestone tasks
- StartToStart - Start to start. Allowed only when both predecessor and successor are Planned tasks
- StartToFinish - Start to finish. Allowed only when predecessor is Planned, and successor is Planned or Milestone task
- FinishToStart - Finish to start. Allowed only when predecessor is Planned or Milestone, and successor is Planned task
Relation between Predecessor and Successor
- FinishToFinish - Finish to finish. Allowed only when predecessor and successor are Planned or Milestone tasks
- StartToStart - Start to start. Allowed only when both predecessor and successor are Planned tasks
- StartToFinish - Start to finish. Allowed only when predecessor is Planned, and successor is Planned or Milestone task
- FinishToStart - Finish to start. Allowed only when predecessor is Planned or Milestone, and successor is Planned task
lagTimenumber
Always in minutes, positive numbers are lag time and negative numbers are lead time
Always in minutes, positive numbers are lag time and negative numbers are lead time
Response
success response